Park completes VSP nomination/PMIS form on SCC
Prioritized by Regional Office
VSP Advisory Committee reviews & recommends to WASO
Approval by WASO
Park authorizes $ to UI-PSU-VSP
Questionnaire design workshop
(3-4 hours)
Draft Questionnaire
(1 month)
Social Science/OMB Approval
(2 months)
Conduct fieldwork
(7-10 days)
Await incoming questionnaires/
Send follow-ups
(3 months)
Data analysis
(2 months)
Draft report
(1 month preparation;
1 month park review)
Final report
(1 month)
Results workshop
(1-2 hours)
Additional analysis, if requested
(varies)
Superintendent evaluates the VSP