The VSP process usually takes 1+ years from questionnaire development to final report. Download a PDF version at the bottom of this page.

Park superintendent submits online nomination/PMIS form 

Approval by WASO

Park authorizes $ to UI-PSU

Questionnaire design workshop
see VSP Question database: https://vsp.uidaho.edu
(1-2 hours)

Draft Questionnaire
(1 month for park review) 

Social Science/OMB approval
(6-8 months)

Conduct fieldwork
(usually 7 days)

Await incoming questionnaires/
Send follow-ups
(3 months)

Data entry/scanning/analysis
(2 months)

Draft report
(1 month preparation;
1 month park review)

Final report
(1 month)

Results workshop(s)--park staff and community 
(1.5 hours)

Additional analysis, if requested
or search on VSP database: https://vsp.uidaho.edu

Superintendent evaluates VSP work

Download:  VSP_timeline2012.pdf

 

 

 